Project Scope Management
Time Management
Stakeholder Management

Project Scope Management

According to the Project Management Institute (PMI), project scope management includes the processes of defining, controlling, and documenting what is and what is not included in the project. The following requirements/scope traceability matrix provides a means for tracking all the key scope changes to date for the COCONet project.

                         
Change Authorization and DateNew StationsRefurbishedExistingOther ChangesNotes / Rationale for Inclusion
Original Proposal
Approved July 2010
50 0 50
COCONet Workshop for Community Science, Station Siting, and Capacity Building San Juan, Puerto Rico
February 3-4, 2011
- - - Due to stakeholder recommendations, roof top GPS monuments will be considered. Original proposal called for short drilled braced monuments.
2011 COCONet Network Operators Meeting Port of Spain, Trinidad
June 28-29, 2011
50 15 61 The concept of the “refurbished” station introduced. Final siting plan developed.
2011 COCONet Network Operators Meeting Port of Spain, Trinidad
June 28-29, 2011
- - - Siting Committee Formed
COCONet Project Director
July, 2011
- - - Switched to Zephyr antenna (no radome) This change was required due to budget impact of the 15 refurbished stations identified in Trinidad.
COCONet Siting Committee
October 21, 2011
49 17 61 CN05 Punta Cana removed. Two more refurbished stations were added in the Dominican Republic, LVEG and SPED.
COCONet Siting Committee
November 22, 2011
48 18 61 CN19 Guanaja removed. This site was considered redundant with the existing station at Roatan (ROA0). ROA0 will be upgraded and considered a refurbished station.
COCONet Siting Committee
February 21, 2012
47 18 61 CN04 St. Croix removed. There are already two existing stations there; one of which is a GGN station.
COCONet Project Director
September, 2012
- - - Switched back to choke ring with radome This change was possible due to savings elsewhere in the budget.
COCONet Field Operations Manager / Project Director
September 2012
- - - Waterproof Pelican-Hardigg enclosure approved for installation in Jamaica. Enclosure is exposed to sea spray due to proximity to the ocean. New enclosure is sealed, with one-way venting.
COCONet Siting Committee
October 1, 2012
46 21 61 CN20 (Cayman Brac) removed. COCONet will provide meteorological instruments for 3 existing stations operated by Government of the Cayman Islands.
NSF Program Manager
August, 2012
54 21 61 2 new tide gauge stations, with new GPS on the pier and within .5km of the pier. NSF approved the installation of two new tide gauge instruments (with 2 GPS stations) and to install 2 new GPS stations at the 2 existing tide stations in the region.
COCONet Siting Committee
Approved
55 21 61 Add CN05 (Punta Cana), can be done due to savings elsewhere in the budget.
COCONet Siting Committee
Approved
56 21 61 Add new station in Aruba.
COCONet Siting Committee
Approved
57 21 61 Add new station in Panama (Bocas Island).
COCONet Working Group
Approved
58 21 61 Added new station at Aves Island. Discussed in Trinidad.
COCONet Working Group
Approved
58 17 61 Removed 4 refurbished stations in Venezuela from installation plan.
COCONet Working Group
Approved
59 17 61 Added new station in St. Lucia. Discussed in Trinidad.Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 17 61 Approval not likely for second station in Cuba. Removed station from plan. Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 17 61 Approval not likely for second station in Cuba. Removed station CN17 from plan. Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 18 61 Added refurbished station in Grand Turk (GTK0). Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 19 61 Added refurbished station in Antigua (Mount Obama). Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 20 61 Added refurbished station in Haiti (JME2). Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 21 61 Added Maracaibo (MARA) as refurbished station (originally was existing). Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 20 61 Removed GALE (Trinidad) - this station was upgraded by UWI, will contribute data to COCONet. Approved at COCONet Working Group Meeting - 4/1/2014
COCONet Working Group
Approved
58 20 61 Station FORT moved to UWI campus in Trinidad - No change to station count. Approved at COCONet Working Group Meeting - 4/1/2014